Operating AI data center in New Albany, Ohio, run by Meta.
471 MWpower capacity today
1 GWplanned capacity
~357,583homes' worth of electricity
~1 milliongallons of cooling water a day (est.)
Details
Where
New Albany, OH (approximate location)
Owner / operator
Meta
Running for
1 year (since Oct 2025)
Power
471 MW now, 1 GW planned
Power from
AEP Ohio, plus on-site gas (Williams)
Footprint
Not published
Noise
No decibel readings published for this site. Large data centers often run above 60 dB near homes, and backup generators can reach about 105 dB during tests.
Note
Meta's 1 GW supercluster; on-site gas generation planned.
Energy and water figures are estimates based on power capacity and US averages.
What it could mean for power bills
Ohio makes data centers pay for 85% of reserved power
Ohio regulators approved an AEP Ohio tariff requiring new data centers to pay for at least 85% of the power they reserve, even if they use less, for up to 12 years. The goal is to keep other customers from paying for grid upgrades built for them.
In PJM, the grid serving 13 states from Illinois to New Jersey, a record capacity auction pushed power costs up, with data centers named the main driver. Monthly bills were expected to rise more than 5%; in Columbus, Ohio, about $27 a month.
The US Energy Information Administration expects average home electricity prices to reach 18.2 cents per kWh in 2026, almost 5% higher than 2025, with demand from businesses including data centers a key reason. Some East Coast areas may see up to 7% a year.